Search found 13 matches

by anand.sutar
Fri Jun 14, 2019 1:34 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Finally I Achieved PMP Certification
Replies: 3
Views: 442

Re: Finally I Achieved PMP Certification

Dear all, Regret for my delayed experience sharing process. I cleared PMP Exam on 23rd April 2019, with below score Initiation – AT, Planning – AT, Execution – T, M&C – T, Closing – AT. Major lesson learned is, study required proper planning, dedication, developing stamina for physical, mental l...
by anand.sutar
Tue Apr 23, 2019 10:02 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Finally I Achieved PMP Certification
Replies: 3
Views: 442

Finally I Achieved PMP Certification

Just Passed PMP Certification on 23 April 2019,
Detailed Lessons Learned will update soon.

Overall difficulty level not so high, compare to iZen Bridge mock test 2.

But questions are tricky.
by anand.sutar
Sat Mar 23, 2019 5:40 am
Forum: PMP® Open Forum
Topic: Expected Monetary value
Replies: 3
Views: 1480

Re: Expected Monetary value

Option C suppose to be negative value, means,

(-$11175)
by anand.sutar
Sun Feb 17, 2019 7:14 am
Forum: PMP® Exam Lessons – Success Stories
Topic: How I Earned My PMP Certification!
Replies: 4
Views: 857

Re: How I Earned My PMP Certification!

Thank you Chetan for sharing detailed experience and further guidance.

Congrulations... :D
by anand.sutar
Fri Feb 01, 2019 1:50 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed the PMP exam
Replies: 19
Views: 7067

Re: Passed the PMP exam

Congrutulations, Kaushal for clearing the PMP.
Thank you, for sharing a detailed experience and issues you faced during preparatons. Definately your shared knowledge will be guide to many PMP aspirants. :)
by anand.sutar
Mon Jan 07, 2019 2:36 pm
Forum: PMP® Queries and Tips
Topic: Procurement Mangement Question Solve pattern
Replies: 3
Views: 1774

Re: Procurement Mangement Question Solve pattern

Manish Sir, based on you suggesting, I understood below path, correct me if I am wrong, question can be solved purely based on Elimination technique by understanding two things, 1st) question in which process, its in Conduct Procurement, so eliminate rest options A and D, and 2nd) What PM actually d...
by anand.sutar
Sun Jan 06, 2019 2:28 am
Forum: PMP® Queries and Tips
Topic: Control Cost EVM Formula
Replies: 0
Views: 355

Control Cost EVM Formula

Dear Manish Sir, regarding Control Cost EVM Formula specially EAC After going thru Saket Sir old video on EVM and your suggestions of forum, I considered below conditions as per four formulas, EAC=BAC/CPI When to use conditions 1. If question giving sufficient hint about, current CPI will not change...
by anand.sutar
Sun Jan 06, 2019 2:28 am
Forum: PMP® Queries and Tips
Topic: Cost Estimates as per phases
Replies: 1
Views: 1297

Cost Estimates as per phases

Dear Manish Sir, I feel, below phase wise cost estimation calculations, kindly guide. Initiation: ROM: -25% to +75% & (while developing Project Charter) Preliminary Estimate: -15% to +50% or based on Project type, but generally between ROM or Preliminary Estimate Planning: Budget Estimate: -10% ...
by anand.sutar
Sun Jan 06, 2019 2:27 am
Forum: PMP® Queries and Tips
Topic: Close Project / Phase sequence
Replies: 1
Views: 1286

Close Project / Phase sequence

Dear Manish Sir, I searched on forum regarding sequence for close project, got below Confirm work is done to requirements.>Gain formal acceptance of the product - this is Validate scope> Complete financial closure. Towards Seller> Hand off completed product (Hand over to Ops)> Complete procurement c...
by anand.sutar
Mon Dec 24, 2018 6:05 am
Forum: PMP® Queries and Tips
Topic: Procurement Mangement Question Solve pattern
Replies: 3
Views: 1774

Procurement Mangement Question Solve pattern

Dear Seema, Manish or Saket Sir, I just wanted to know is my undertanding of solving question is proper or need to be improved, example is as below, Question is from Rita Book, Procurement Management assessment question No. 27) 27) Your project has just been fast tracked, and you are looking to quic...
by anand.sutar
Sat Oct 20, 2018 6:15 am
Forum: PMP® Queries and Tips
Topic: Lessons learned
Replies: 2
Views: 813

Re: Lessons learned

I feel the words in each answer are most important rather that the standard guildline, option C and D is clearly wrong answers. so option A and B left, option B is, B. This is not ok. Lessons learned must be documented all through the project as well as at the end of the project. this statment puts ...
by anand.sutar
Wed Oct 03, 2018 4:11 am
Forum: PMP® Open Forum
Topic: Conduct Procurement
Replies: 4
Views: 1805

Re: Conduct Procurement

Lesson learned is, This is more than one minute question, and need to understand the situation and as per situation associate factors to whom we suppose to deal. Situation is regular order, so regular order it is a repetitive work, so MOSTLY no one will do the market research, since it’s may be alre...
by anand.sutar
Sat Sep 22, 2018 8:45 am
Forum: PMP® Queries and Tips
Topic: Schedule
Replies: 5
Views: 2358

Re: Schedule

In my opinion, (correct me If I am wrong.) Issue is PMP ask Tricky question not straight forward. Here, Situation is "Today, Project office indicated that some of resouces are not avaiable." Here it is not explained that these resouces which was planned are impacting Critical Path or not, ...

Go to advanced search